Regional Consultancy Support

Supplemental Capacity Preparing a Materials Management Plan and Support on Gasworks Remediation

Background

A medium sized regional environmental consultancy was supporting a property company developing a former gasworks site.

Objectives

RemTech provided some additional capacity during a busy period for the consultancy.  Our depth of expertise in gasworks remediation supplemented the project team at little extra cost.

Project Summary

Client:
Regional Environmental Consultancy

Project Duration and Cost:
10 days – £2,000

Key Services:

RemTech drafted the project Materials Management Plan under DoWCoP and advised on the identification and excavation of gasworks below ground structures as part of the discovery strategy.  We visited site on several occasions to assist in the implementation of the MMP.

Outcome:
Additional gasworks structures were found during the remediation but were successfully removed and the project was completed on time and within budget.